WSJF.

Score the three parts of cost of delay, divide by job size, and rank the backlog by what is most expensive to postpone.

WSJF = cost of delay ÷ job size, where cost of delay = user-business value + time criticality + risk reduction and opportunity enablement. Score each on the modified Fibonacci scale (1, 2, 3, 5, 8, 13, 20) relative to the other items, never in absolute units.

—WSJF score
—Cost of delay

Enter values to calculate.

Sequence by economics.

Conyso Consulting installs the Agile and flow practices that put cost of delay into real prioritisation calls.

Talk to Conyso Consulting →

How it works

The method.

WSJF = cost of delay ÷ job size, where cost of delay = user-business value + time criticality + risk reduction and opportunity enablement. Score each on the modified Fibonacci scale (1, 2, 3, 5, 8, 13, 20) relative to the other items, never in absolute units.

72/ 1000100
A value read on a 0–100 scale.

FAQ

WSJF, answered.

What is WSJF?

Weighted shortest job first, the prioritisation method in SAFe. It ranks backlog items by cost of delay divided by job size, so the work that is most expensive to postpone relative to its effort goes first.

What is the WSJF formula?

WSJF = cost of delay ÷ job size. Cost of delay is itself the sum of three estimates: user-business value, time criticality, and risk reduction or opportunity enablement.

How do you calculate WSJF, with an example?

Score an item 8 for business value, 5 for time criticality and 3 for risk reduction: cost of delay is 16. Divide by a job size of 5 and WSJF is 3.2. An item scoring 20 in total against a job size of 13 scores 1.54, so the first item is sequenced ahead of it.

What scale should the WSJF inputs use?

The modified Fibonacci scale, 1, 2, 3, 5, 8, 13 and 20. The numbers are relative to the other items in the backlog, not absolute units, and the smallest item in each column should be anchored at 1.

Why divide by job size instead of prioritising by value?

Because a slightly less valuable item that takes a fraction of the effort delivers value sooner and frees capacity. Dividing by job size is what makes it shortest job first rather than highest value first.

Is WSJF only for SAFe?

No. It was formalised in SAFe and is most used there, but the underlying idea, sequencing by cost of delay against duration, comes from product development flow and works on any backlog where you can estimate both.